The Regional Transportation Commission (RTC) of Washoe County is set to begin construction on phase one of a four phase project of the Oddie Wells Multimodal Improvements on Monday, November 29, 2021.

The project is expected to increase safety, connectivity, and mobility options along this heavily traveled corridor.

The project plans include new lighting, landscaping, ADA improvements, pedestrian ramps, and bicycle facilities, providing safer traffic operations.

The RTC plans to construct a raised cycle track on both sides of the roadway from Sutro Street in Reno to Pyramid Way in Sparks.

On Wells Avenue from Sutro Street to I-80, plans include a multiuse pathway on one side of the road and sidewalks on the other side.

The new multiuse pathway will connect to the existing multiuse pathway along I-80 by UNR Farms.

Construction will begin at the Oddie Boulevard/Pyramid Way intersection in Sparks and move westward towards the Wells Avenue/I-80 intersection in four phases to minimize the impacts to the traveling public:

 

  • November 2021 - Phase 1: Pyramid Way to Sullivan Lane
  • Fall 2022 - Phase 2: Sullivan Lane to Silverada Boulevard
  • Summer 2023 - Phase 3: Silverada Boulevard to Sutro Street
  • Spring 2024 - Phase 4: Sutro Street to I-80 on- and off-ramps

 

The RTC and its contractor, Granite Construction, may work on adjacent phases at the same time.

Construction at major intersections in anticipated and detour information will be provided in advance.

All construction operations are weather permitting and completion is anticipated in the fall of 2024.

(The Regional Transportation Commission assisted in this report.)

 